BOQ-10222 — Master Power to Airtel MSC

Client: WIOCC · Location: Ibadan, Nigeria · Duration: 23 Business Days · InProgress

Bill of Quantities — Line Items

Budget ₦12,000,000
S/NDescriptionUnitQtyRateAmount
1ROW Permits & RegularisationLot1 ₦450,000₦450,000
2Manhole Marking (250m intervals)No.10 ₦15,000₦150,000
3Manhole Construction (1x1x1.2m ext.)No.10 ₦180,000₦1,800,000
4Trenching (1m x 450mm)m1,593 ₦950₦1,513,350
5Trench Casting (concrete)m667 ₦2,100₦1,400,700
6Thrustboring (road crossings)m219 ₦4,200₦919,800
7Duct Laying (1x40mm)m1,812 ₦620₦1,123,440
896F G.652D HDD Cable Supply & Haulm2,474 ₦1,450₦3,587,300
9Splicing / Termination (96-core)Lot2 ₦320,000₦640,000
10As-Built DocumentationLot1 ₦150,000₦150,000
TOTAL₦11,734,590
Actual spend to date across this BOQ is tracked on the project detail page (Expenses tab): ₦9,557,000 of ₦12,000,000 (79.6%).