BOQ-10222 — Master Power to Airtel MSC
Bill of Quantities — Line Items
Budget ₦12,000,000| S/N | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | ROW Permits & Regularisation | Lot | 1 | ₦450,000 | ₦450,000 |
| 2 | Manhole Marking (250m intervals) | No. | 10 | ₦15,000 | ₦150,000 |
| 3 | Manhole Construction (1x1x1.2m ext.) | No. | 10 | ₦180,000 | ₦1,800,000 |
| 4 | Trenching (1m x 450mm) | m | 1,593 | ₦950 | ₦1,513,350 |
| 5 | Trench Casting (concrete) | m | 667 | ₦2,100 | ₦1,400,700 |
| 6 | Thrustboring (road crossings) | m | 219 | ₦4,200 | ₦919,800 |
| 7 | Duct Laying (1x40mm) | m | 1,812 | ₦620 | ₦1,123,440 |
| 8 | 96F G.652D HDD Cable Supply & Haul | m | 2,474 | ₦1,450 | ₦3,587,300 |
| 9 | Splicing / Termination (96-core) | Lot | 2 | ₦320,000 | ₦640,000 |
| 10 | As-Built Documentation | Lot | 1 | ₦150,000 | ₦150,000 |
| TOTAL | ₦11,734,590 | ||||